5月8日,海瑞克用于新加坡地铁跨岛线二期CR202项目的开挖直径12.78米混合式盾构机具备始发条件并开始拼装负环。
On 8th May 2025, the Herrenknecht Mixshield with a excavation diameter of 12.78-meter, designed for the Cross Island Line Phase 2 CR202 project in Singapore, was ready for operations and started with Temporary Ring erections!
项目介绍
Project Overview
新加坡地铁跨岛线二期工程(下简称CRL2)全长约15公里,全地下敷设6个地铁站。CR202项目作为CRL2的一部分,将采用海瑞克混合式盾构机在美丽岛通道和新民径之间建造一条全长约5公里的大直径单洞双轨地铁隧道,该隧道建成后将成为新加坡境内由单台盾构机进行连续掘进的最长隧道。
The Cross Island Line Phase 2 (CRL2) spans 15 kilometers with 6 fully underground stations. As a part of CRL2, CR202 will involve the tunnelling of a double-track, single-bore metro tunnel approximately 5 kilometers between Fairways Drive and Sin Ming Walk using the Herrenknecht Mixshield. Upon completion, this tunnel will be the longest drive by a single TBM in Singapore.
图片来源业主官方Instagram账户
Source: LTA Official Instagram
项目挑战
Project Challenges
作为目前新加坡最长的盾构法大直径双轨单洞地铁隧道,CR202项目包含2公里深入地下、穿越中央集水地带自然保护区的隧道段。该工程周边地质条件复杂,工法要求多样,是新加坡地下工程史上最具挑战的隧道项目之一。
隧道掘进过程中,主要穿越微风化花岗岩层,其岩石最高强度达290 MPa。为应对极端地质条件,盾构机采用耐磨刀盘并优化滚刀间距以实现高效岩石切割;配备的滚动碎石机可将岩石破碎成更小颗粒,从而保障泥浆顺畅排出;开挖仓内还配置了特殊伸缩摄像系统,可在无需高压干预的情况下实时监控刀具、刀盘及掌子面状态。此外,盾构机搭载的半连续掘进系统(SCA)支持同步拼环与隧道掘进作业,可显著提升掘进效率。
As Singapore’s longest large-diameter double-track, single-bore tunnel by tunnelling method, a 2-kilometer section of the tunnel will pass under the Central Catchment Nature Reserve. The geological conditions surrounding the project are complex, and the construction methods required are diverse, making it one of the most challenging tunnel projects in Singapore's history of underground engineering.
When tunnelling, fresh granite with a UCS of up to 290 MPa. To cope with the extreme geological conditions, the TBM is especially equipped with a wear-resistant cutterhead with optimized disc cutters’ spacing for efficient rock cutting. Thereafter, a heavy-duty roller crusher crushes the rocks smaller for a smoother slurry discharge. In addition, a special telescopic camera system in the excavation chamber allows to monitor the status of the cutting tools and the tunnel face without the need for hyperbaric intervention. The TBM is also equipped with Semi Continuous Advance system to perform ring building and TBM advance concurrently, thereby increasing the tunnelling efficiency.
项目意义
Project Significance
新加坡地铁跨岛线二期工程(CRL2)的建成,将显著提升新加坡西部地区交通通达性,通过新增6个地下车站(含2个换乘站)填补西海岸、裕廊湖区等无地铁覆盖区域的空白;其与滨海市区线、东西线的换乘衔接将强化东西部及东北部区域联动,分散全网客流压力。
The completion of Singapore's Cross Island Line Phase 2 (CRL2) will significantly enhance transport accessibility in western Singapore. By adding 6 underground stations (including 2 interchange stations), CRL2 will fill current metro service gaps in areas like West Coast and Sunset Way. CRL2’s interchanges with the Downtown Line and East-West Line will strengthen connectivity between eastern, western and northeastern regions, while helping redistribute commuter loads across the entire rail network.
项目回顾
Project Recap
2024.5.24
2024年5月24日,海瑞克用于新加坡地铁跨岛线二期 CR202项目的大直径混合式盾构机在海瑞克广州南沙工厂顺利通过验收,正式下线!
On 24th May, a Herrenknecht large-diameter Mixshield for Singapore MRT Cross Island Line (CR202) project successfully passed the factory acceptance test and held the ceremony at Guangzhou Herrenknecht Tunnelling Machinery Co.,Ltd!
2025.3.10
2025年3月10日,盾构机刀盘在工地现场顺利下井。
On 10th March 2025, the cutting wheel of TBM was successfully lowered into the shaft at the jobsite.
项目数据
Project Data
机器类型:1 x 混合式盾构机 S-1365
开挖直径:12780mm
刀盘功率:7000kW
掘进长度:5000m
地质状况:硬岩、软土、花岗岩
业主:新加坡陆路交通管理局
承建商:大林组株式会社与上海隧道工程股份(新加坡)有限公司联营体
Machine type: 1 x Mixshield S-1365
Excavation Diameter: 12,780 mm
Cutterhead drive power: 7,000 kW
Tunnelling length: 5,000 m
Geology: Hard Rock, Soft Soil, Granite
Client: Land Transport Authority
Contractor: Obayashi Corporation and Shanghai Tunnel Engineering Co (Singapore) Pte Ltd JV